June 14, 2024

Construction Update for Week Ending 06.14.24


The inside work at the elementary school is scheduled for next summer. We will start the outside construction later in July of this year. This summer we will focus on the inside work atthe Jr/Sr High School and the athletic fields.

Week Ending 06.14.24:

Since the school year for students & staff ended last Friday, this has been our first week ofconstruction activity at the Jr/Sr High School. A few of the highlights currently in process are:

  • Removal of all the flooring in the hallways and cafetorium
  • Demolition of the science classrooms
  • Demolition of the greenhouse
  • Painting of the main gym

We will do our best to take pictures along the way. Here are a couple for this week:

  • The demolition of the greenhouse
  • The start of removing the ball field fence